NV Energy has halted work on key sections of its Greenlink West transmission line, a major renewable energy project in Nevada. The pause comes after the U.S. Air Force raised concerns that the new power lines could interfere with military training and testing operations. The project's completion is now delayed until May 2027.
Key Takeaways
- NV Energy has paused construction on parts of the 470-mile Greenlink West transmission line.
- The delay is due to U.S. Air Force concerns about potential interference with operations at Nellis Air Force Base.
- The project's estimated completion date has been pushed from late 2026 to May 2027.
- The transmission line is designed to carry renewable energy, primarily from solar projects, to power over 4 million homes.
Details of the Project Delay
The Greenlink West project, a 470-mile high-voltage transmission line connecting Las Vegas and Reno, is a critical component of Nevada's renewable energy infrastructure. However, construction has been temporarily suspended in certain areas while NV Energy negotiates with the Department of Defense.
The primary issue involves the height of the transmission towers, some of which are designed to be over 100 feet tall. The Air Force has expressed concern that these structures could disrupt flight training and weapons testing exercises conducted from Nellis Air Force Base, a major military installation in southern Nevada.
A High-Priority Infrastructure Project
The Greenlink West transmission line is considered a top priority for the Biden administration's clean energy goals. Its purpose is to unlock vast renewable energy resources, mainly solar power, in rural parts of Nevada and deliver that electricity to population centers. The project received federal approval from the Bureau of Land Management (BLM) in September 2024.
Negotiations Between NV Energy and the Military
The Bureau of Land Management is now facilitating discussions between NV Energy and the Department of Defense to find a solution. The goal is to identify potential adjustments to the power line's route or design that would mitigate the impact on military operations without compromising the project's objectives.
"We are in a holding pattern until we can get clearance from the military," Shahzad Lateef, NV Energyβs project director, stated at a recent Beatty Town Advisory Board meeting.
This statement, recorded during the public meeting, highlights that progress on the affected sections is entirely dependent on reaching an agreement with defense officials. The utility is waiting for a resolution before proceeding with construction in the sensitive areas.
Impact on Nevada's Energy Future
The delay represents a significant challenge for a project intended to bolster the state's energy grid and support its transition to cleaner power sources. Upon completion, the Greenlink West line is expected to have the capacity to transmit enough electricity to power more than 4 million homes.
Project at a Glance
- Length: 470 miles
- Route: Las Vegas to Reno, Nevada
- Capacity: Power for over 4 million homes
- Primary Energy Source: Solar
- New Completion Date: May 2027
The project is not only vital for meeting renewable energy targets but also for improving the reliability of the electrical grid across the state. By connecting southern and northern Nevada, it allows for more efficient distribution of power, particularly from large-scale solar farms in the south.
The Role of Nellis Air Force Base
Nellis Air Force Base is home to the U.S. Air Force Warfare Center and hosts advanced aerial combat training exercises, such as Red Flag. The expansive Nevada Test and Training Range, which is associated with the base, is used for testing advanced weaponry and aircraft.
The concerns raised by the Air Force are centered on ensuring that these critical national security activities can continue without obstruction. The height and location of the transmission towers are being carefully reviewed to prevent any potential hazards to low-flying aircraft or interference with sensitive testing equipment.
Next Steps and Revised Timeline
NV Energy has affirmed its commitment to working collaboratively with the military to resolve the issues. The utility is exploring alternative routes and engineering solutions for the sections of the line near the military's operational areas. The revised completion date of May 2027 reflects the anticipated time needed for these negotiations, potential redesigns, and subsequent construction.
While the delay is a setback, all parties involved are engaged in finding a path forward. The outcome of these discussions will be crucial for balancing the nation's energy needs with its national security interests.





